NASA has completed the stacking of the center segments for both Artemis III solid rocket boosters on Mobile Launcher 1, marking a significant milestone in the preparation for the mission targeted for no earlier than June 2027.

What Happened

The stacking process began in July inside the Vehicle Assembly Building, with the first pair of aft segments placed on July 13. The right aft-center segment was installed on August 12, followed by the center segments on August 20, with the right booster stacked first and the left second. Two motor segments remain for each booster, which will be capped by nose cones and forward skirts currently awaiting installation in the building.

Concurrently, teams in High Bay 2 are preparing the Core Stage. The tank section arrived from New Orleans in the spring and was mated to the engine section shortly after, with RS-25 engine installation now underway. At the Operations and Checkout Building, engineers completed umbilical connections between the Artemis III Orion crew module and its European Service Module, successfully powering the crew module for the first time to confirm electrical connectivity.

At Marshall Space Flight Center, work continues on a spacer to replace the Interim Cryogenic Propulsion Stage, which is not required for this mission. Welding of the spacer barrel finished several weeks ago, and the forward ring connecting to the Launch Vehicle Stage Adapter has been added. For Artemis III, NASA plans to fly structural test articles for the Launch Vehicle Stage Adapter and Orion Stage Adapter, reserving flight units for Artemis IV. The Orion Stage Adapter is currently receiving paint and insulation preparation for installation next year.

Why It Matters

Artemis III is scheduled to carry a crew of four and the Orion spacecraft to test lunar modules alongside it, though it will not land on the Moon. The progress on Core Stage 4, assigned to Artemis IV (planned for 2028), shows the pipeline extending beyond the immediate mission. The liquid hydrogen tank for Core Stage 4 has completed proof testing at the Michoud Assembly Facility and is being cleaned for outfitting. For Artemis V, the engine section barrel has been moved into the Vertical Assembly Center for mating with the liquid hydrogen tank.

Hardware production has also begun for the Core Stage associated with Artemis VI, despite NASA’s stated plan to transition to commercial vehicles for crew flights to lunar orbit after Artemis V. A connecting ring for Core Stage 6 is in work as a contingency if commercial alternatives are not ready, though it is not yet clear if this hardware will proceed to a completed stage. The engine section remains the most complex part of the Core Stage and is the furthest along in production.

The Bottom Line

NASA is advancing multiple layers of Artemis hardware simultaneously, from booster stacking and Orion integration for Artemis III to early production for subsequent missions. While Artemis III is targeted for mid-2027, contingency work on Core Stage 6 reflects ongoing uncertainty about the timeline for commercial lunar transport alternatives.